← Back to All ProjectsProject #11 of 13 • Executed by SGE
Audited Contract Value₹43.70 Lacs
Commencement Date29-May-2025
Stipulated & Actual Completion6 Months (30-Nov-2025)
Arbitration / Litigation StatusNil / Clear
Executive Engineering Summary
Completed a ₹43.70 Lacs turnkey MEP package for Coalesce Management Services Pvt. Ltd. (MDLR), integrating heavy electrical distribution, automatic fire suppression headers, and commercial piping infrastructure.
Heavy ElectricalsFire SuppressionPiping
Detailed Technical Scope of Work
- Main fire pump room installation, suction/delivery headers, and automation panels.
- Multi-floor sprinkler grids, hydrant risers, and external yard hydrants.
- Electrical panel boards, cable trays, and earthing network.
- Comprehensive testing, commissioning, and handover documentation.
Plant Room & Infrastructure Gallery
Client Details
Sponsoring Organization
Coalesce Management Services Pvt. Ltd. / MDLR
MDLR Campus, Gurugram, Haryana
System Parameters
Technical Specifications
ClientCoalesce Management Services / MDLR
Contract Value₹43.70 Lacs
Timeline6 Months (May 2025 – Nov 2025)
ScopeTurnkey Fire, PHE & Electrical
Verified Credentials
Official Contract Documents
Inspect the official signed work orders and completion certificates issued for this project.